Work continues on the Awae-Esse-Soa section. The CFHEC company, although still awaiting the signing of its contract, is maintaining its pace of work.
Since the first two weeks of March, the purges already carried out on the Esse-Soa section have been gradually filled in with rubble, particularly at PK 26+000.
Over almost 2km, rehabilitation work on the platform is also being carried out. Still on this same Esse-Soa route, the company has started the implementation of the foundation layer starting from PK 18+750 to PK 19, over approximately 1km.
On the Awae-Esse section, it is in particular the ordinary and rock excavation activities which characterize the earthworks in progress over 7km. This work continues to be carried out under the supervision of the control mission and the satisfaction of the local populations.