Babadjou-Matazem section: the company completes the road work and continues the signage



On this first section of the Babadjou-Bamenda road, the user can easily drive over the entire 17 km which constitute this lot. The road work is fully completed and the Bun’s company is currently finalizing the horizontal signage.


If on March 15, 2024 the progress of work on the main road was estimated at 93% at the end of the first decade of April 2024, this rate is close to 100%. The company is working to complete the construction work on the associated tracks which cover a total length of 10.5 km.

 

Clément Noumsi