top of page
Cosmétiques au romarin

Bafang-Nkondjock road: the company’s execution project is awaited

While the company CETP SARL completes the construction of certain works, in parallel with the treatment of quagmires identified on the route, it must also transmit its execution project.



The work actually started the day after the company's notification, on March 22, 2024. Overall, two teams are deployed to treat critical points along the route, with the aim of avoiding disruptions. traffic. As of April 15, 2024, the progress of the work is estimated at 11.14% for a time consumption of 6.67%.

The project review opened on April 18, 2024 made it possible to assess the company's mobilization on the ground and, moreover, the progress of the work in relation to market performance. For this phase 1, the work must extend over twelve months and focus on clearing the road, cleaning, deforestation, road work and treatment of the road, including the construction of the structures. On the financial side, the company has so far received no payment and a start-up advance statement in the amount of 148,502,165 CFA francs has been issued and remains awaiting payment. The work is carried out by the company CETP SARL, under the control of the Ingénierie Conseil/Arsuk SARL group..


Reaction



Thomas Ntouko, head of control mission of the Engineering Conseil/Arsuk group


« Currently we are at the start of the work, the staking of the axis has been carried out and received by the control mission. The company started the work on March 11 before the service order was notified to start the work. He had already started from Pk 0 to PK 7 for the organization of the funeral of Minister Ngoupeyou, this was part of the emergency work. Currently, the company is constructing a box culvert at the Pk 20.175 bridge and is treating the quagmires between Pk 26 + 800 to Pk 27 + 100 to facilitate traffic. Likewise, the critical area called the tunnel is being developed. There is also the reprofiling of this place and for the moment we are awaiting the definition of the tasks which will allow the mobilization of the company on the site. Even if there is construction of certain culverts, the work carried out is to currently allow the flow of traffic».

 

Clément Noumsi

3 views0 comments

Comentarios


bottom of page