top of page
Cosmétiques au romarin

Steel bridge under construction at Kekem

The company reports that the work will be installed in 12 days.


The 42.53-meter-long structure is located on the Kekem-Carrefour Tchouaffe factory route and will cross the Ngoum River in the Haut-Nkam region. The project also includes the development of access roads on both sides of the structure, for a total length of 100 ml. According to the company's schedule, the steel bridge, previously assembled from metal elements acquired during the first phase of the project, will be installed in 12 days.

The 464,913,044 f cfa project, carried out by SOTRAM Sarl, is under the technical supervision of the Le Competing/Cameng/Transahelienne consortium, and the geotechnical control of Cabinet TWS Sarl. On site, work is in progress on the technical backfill of the 02 abutments, which is nearing completion, the backfill of the access roads, the riprap and the continued assembly of the deck.

 

Clément Noumsi

4 views0 comments

Comments


bottom of page